@Martyac - I agree that in ground tonnes are different to...

  1. 1,000 Posts.
    lightbulb Created with Sketch. 1167
    @Martyac - I agree that in ground tonnes are different to processed ore tonnes, however, my calcs give production for a little longer than you estimated.

    I note that they are targeting a 9% minimum in ground, so whilst the average could be higher, I have used 9% to allow for some loss in production.

    100Mt in ground at 9% gives 12.8Mt of processed ore at 70% (100Mt times 9% divided by 70%). At planned production of 11Mt per annum, that is 14 months production (12.8Mt divided by 0.916 per month).

    If they find another 140Mt, to have a total of 240Mt in ground at 9%, that gives 30.8Mt of processed ore at 70% (240 times 9% divided by 70%). At planned production of 11Mt per annum, that is 33 months production (30.8Mt divided by 0.916 per month).

    Nearly three years production of near surface ore will make a big difference to an NPV number.
 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.
(20min delay)
Last
1.8¢
Change
-0.002(10.0%)
Mkt cap ! $18.29M
Open High Low Value Volume
2.0¢ 2.0¢ 1.8¢ $18.91K 997.5K

Buyers (Bids)

No. Vol. Price($)
4 257739 1.8¢
 

Sellers (Offers)

Price($) Vol. No.
1.9¢ 208543 3
View Market Depth
Last trade - 15.17pm 20/06/2025 (20 minute delay) ?
HIO (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.