How deceptive,
WKT claims they have started Wet Commissioning on the Crusher circuit (which has no requirements for water, later in the Announcements WKT comes clean and details
"Dry commissioning has also started on equipment within the grinding and flotation circuit and these
commissioning activities will continue in preparation for continuous feed through the entire processing
circuit."
IMO, WKT has not started Wet Commissioning until WKT starts using the water in floatation circuits.
- Forums
- ASX - By Stock
- WKT
- Ann: First ore feed at the Lindi Jumbo Graphite Mine
Ann: First ore feed at the Lindi Jumbo Graphite Mine, page-4
-
- There are more pages in this discussion • 29 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add WKT (ASX) to my watchlist
|
|||||
Last
10.5¢ |
Change
-0.003(2.33%) |
Mkt cap ! $70.48M |
Open | High | Low | Value | Volume |
11.0¢ | 11.0¢ | 10.5¢ | $21.84K | 201.4K |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
12 | 604881 | 10.5¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
11.0¢ | 224492 | 6 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
12 | 604881 | 0.105 |
13 | 607474 | 0.100 |
2 | 120000 | 0.099 |
1 | 130000 | 0.098 |
1 | 1 | 0.097 |
Price($) | Vol. | No. |
---|---|---|
0.110 | 224492 | 6 |
0.115 | 1040750 | 5 |
0.120 | 676697 | 12 |
0.125 | 497166 | 10 |
0.130 | 337943 | 6 |
Last trade - 12.11pm 12/07/2024 (20 minute delay) ? |
Featured News
WKT (ASX) Chart |