MSP commissioning will take more than a week or two....but ignoring that and all the other practicalities.
from STA presentations :
HMC averages 25% zircon, 47% ilmenite, 11% rutile-leucoxene & 17% non-valuables
4 MSP zircon recovery comprises 54.8% into premium zircon and a further 43.9% into zircon concentrate as contained zircon.
using those zircon percentages and recoveries :
hmc reqd 32847 zircon in hmc 25% recovery 54.80% zircon shipment 4500
msp design throughput is abt 27tph hmc
kcf