    MSP commissioning will take more than a week or two....but ignoring that and all the other practicalities.

    from STA presentations :
     HMC averages 25% zircon, 47% ilmenite, 11% rutile-leucoxene & 17% non-valuables
    4 MSP zircon recovery comprises 54.8% into premium zircon and a further 43.9% into zircon concentrate as contained zircon.

    using those zircon percentages and recoveries :
    hmc reqd
    32847



    zircon in hmc 25%



    recovery
    54.80%



    zircon shipment 4500

    msp design throughput is abt 27tph hmc
    kcf
 