I was looking at the ships and timing again.
I figure based on the listed shipping company Banasol is our next ship on the 11th May.
- Trucking started on 24th Dec
- PanAfrican departed on 9th Feb (57 days of trucking to fill the ship)
- Marinicki departed on the 24th Mar (43 days of trucking)
- Ballard departed on the 24th April [4 or so days late due to cyclone] (31 days of trucking)
- Banasol due on the 11th may (should leave around the 13th May) - would be something like 19 days to truck a ship load of ore...?
If they have the ore to fill the Banasol so it departs on the 13th, that's a nice haulage story. They said a ship every 22 days from memory so that would be ahead of schedule.
Banasol should have done its quarantine period by the time it hits Bunbury where I guess it will offload in 5 days before coming down to Geraldton where hopefully it heads in and loads up (no waiting at anchor).
Fingers crossed. GLTAH.
- Forums
- ASX - By Stock
- GWR
- Ann: First Shipment on Track as Iron Ore Stockpile Builds
Ann: First Shipment on Track as Iron Ore Stockpile Builds, page-1001
-
- There are more pages in this discussion • 1 more message in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add GWR (ASX) to my watchlist
(20min delay)
|
|||||
Last
8.0¢ |
Change
0.000(0.00%) |
Mkt cap ! $25.69M |
Open | High | Low | Value | Volume |
0.0¢ | 0.0¢ | 0.0¢ | $0 | 0 |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
1 | 29999 | 8.0¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
8.5¢ | 200000 | 1 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
1 | 29999 | 0.080 |
1 | 10000 | 0.079 |
2 | 120000 | 0.078 |
1 | 131578 | 0.076 |
1 | 41666 | 0.072 |
Price($) | Vol. | No. |
---|---|---|
0.085 | 200000 | 1 |
0.087 | 59687 | 1 |
0.091 | 1260 | 1 |
0.100 | 29000 | 1 |
0.105 | 25001 | 1 |
Last trade - 16.12pm 22/07/2024 (20 minute delay) ? |
Featured News
GWR (ASX) Chart |
Day chart unavailable