re: Ann: Gary 1 24H to be drilled near Gene 1...
Sharks,i was just doing the timeline and to me it's the start of june.Mid-late may is probably poetic licence. I have been watching where the rig has been moving and i thought zavanna would drill Gary after Tiger,but are doing Marty now. Zavanna contracted Nabors rig 668 for the whole year and was going to alternate between stockyard creek and other wells close by. Tiger was spudded on 27/3 and yesterday the rig was released and MIRU on Marty.That's about the same time as the Gene drill. 28 days for drill and just over a week to 10 days to rig up.Six weeks absolute minimum from now IF they are using the same rig by the time they rig up and spud Gary. Cheers.