    					CNU
    25/11/2014 09:21
    GENERAL
    NOT PRICE SENSITIVE
    REL: 0921 HRS Chorus Limited (NS)
    
    GENERAL: CNU: Chorus reduces UFB connection cost guidance
    
    STOCK EXCHANGE ANNOUNCEMENT
    
    25 November 2014
    
    Chorus reduces UFB connection cost guidance
    
    Chorus announced today that it has signed new service company agreements for
    the cost of connections to its ultra-fast broadband network.
    
    The new agreements have enabled Chorus to update its connections cost
    guidance for the current financial year from a previous range of $1,300 to
    $1,500 (excluding layer 2 and for standard installations only), to a new
    range of $1,150 to $1,350 (excluding layer 2 and including standard
    installations and some non-standard single dwelling unit installations).
    
    The new agreements are with Visionstream and Downer for fibre network
    connections to single dwelling unit premises in its Auckland, lower North
    Island and lower South Island UFB areas. Under the contracts, the service
    companies will provide network connections at fixed prices, with those prices
    varying according to agreed deployment types.
    
    Chorus GM Infrastructure Ed Beattie said Chorus has been focused on reducing
    its connection costs now that UFB connections are gaining momentum.
    
    "These new contracts and updated pricing are linked to an ongoing national
    tender process.
    
    "With the experience of about 40,000 connections to the fibre network now
    behind them, daily connection volumes becoming more consistent and new
    deployment methods in use, service companies have been able to identify
    efficiencies earlier than expected," he said.
    
    Visionstream's contracted pricing will apply from 1 December to February
    2016, with the ability to extend the contract to the end of 2019 subject to
    pricing and performance. The contract with Downer is retrospective for the
    period 1 July 2014 to the end of February 2015.
    
    The fixed rates under the Downer and Visionstream agreements will also apply
    to non-standard single dwelling unit connections, with this simplified
    approach enabling some reduction in associated non-standard install costs.
    
    Chorus' tender process is continuing for non-Auckland areas and is expected
    to be concluded by the end of December and implemented by February 2015.
    
    There is no change to Chorus' forecast FY15 'UFB connections and layer 2'
    capex of $105 million to $115 million. While connection costs are expected to
    be lower, connection volumes are currently ahead of budget in the year to
    date.
    
    ENDS
    
    For further information:
    
    Nathan Beaumont
    Media and PR Manager
    Mobile: 021 243 8412
    Email: [email protected]
    
    Brett Jackson
    Investor Relations Manager
    Phone: +64 4 896 4039
    Mobile: +64 (27) 488 7808
    Email: [email protected]
    End CA:00258040 For:CNU    Type:GENERAL    Time:2014-11-25 09:21:50
    				
 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.