NZR 17/09/2015 15:42 GENERAL NOT PRICE SENSITIVE REL: 1542 HRS The New Zealand Refining Company Limited GENERAL: NZR: Collective Agreement Refining NZ is pleased to confirm that it has reached agreement with First Union and the EPMU on a three year collective agreement ending June 2018. During negotiations the progress of staff training on the Te Mahi Hou project (TMH) had slowed. As a result, the Company now expects TMH to be commissioned mid to end-November instead of early to mid-November, as communicated in April 2015, still earlier than the project plan that we have reported against over the past three years. ENDS For further information: Greg McNeill Communications & External Affairs Manager T: (09) 4325115; M: 021 873623; E: [email protected] End CA:00270332 For:NZR Type:GENERAL Time:2015-09-17 15:42:49