    REL: 0830 HRS Transpower New Zealand Limited
    
    GENERAL: TRP: North Island Grid Upgrade Project - Update on expenditure
    
    Transpower advises that the final cost for its North Island Grid Upgrade
    Project is forecast at up to $894million. Transpower had previously disclosed
    in its Half Yearly Report to 31 December 2011 that the cost was forecast to
    be
    up to $864million, being the best estimate of the total end cost at that
    time.
    
    The North Island Grid Upgrade Project involves the construction of a 186km,
    400 kV capable overhead transmission line from Whakamaru, north of Lake
    Taupo, to Pakuranga, on the south-eastern side of Auckland, with associated
    substations and underground cables. It will provide a more secure and diverse
    
    supply into the Auckland region.
    
    The increases are largely in the cost of construction of the overhead
    transmission line and the acquisition of associated property rights along the
    line.
    
    For further information, please contact:
    Rebecca Wilson, Corporate Communications Manager, 04 590 6695; 021 578
    608
    End CA:00222977 For:TRP    Type:GENERAL    Time:2012-05-18 08:30:08
    				
 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.

Currently unlisted public company.

arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.