TRP 23/03/2012 08:42 GENERAL REL: 0842 HRS Transpower New Zealand Limited GENERAL: TRP: Wairakei-Whakamaru C line commissioning date Transpower advises that it has now developed its full construction plan for the new Wairakei-Whakamaru C replacement line, and is projecting a November 2013 commissioning date. Civil works will begin next month. The original Grid Upgrade Plan (December 2008) had assumed an earlier start date and an April 2013 commissioning. The principal remaining uncertainty is the acquisition of all appropriate property rights from private land owners along the line: the outcomes of these negotiations could lead to an earlier or later commissioning date. End CA:00221072 For:TRP Type:GENERAL Time:2012-03-23 08:42:13