    • Release Date: 31/10/11 11:00
    • Summary: GENERAL: VCT: Maui pipeline Critical Contingency ends
    • Price Sensitive: No
    • Download Document  1.21KB
    					
    
    VCT
    31/10/2011 09:00
    GENERAL
    
    REL: 0900 HRS Vector Limited
    
    GENERAL: VCT: Maui pipeline Critical Contingency ends
    
    Maui pipeline Critical Contingency ends
    
    Following final tests and independent certification of the repairs to Maui
    Development's
    pipeline, Vector began purging and re-pressurisation of the pipeline in the
    early hours of
    Sunday morning.
    The Critical Contingency Operator (CCO) was then able to advise retailers the
    restoration
    of gas to all customers could commerce in an orderly and managed way.
     Vector Chief Executive Simon Mackenzie said Vector staff have been working
    around the
    clock to repair the Maui Pipeline.
     "We have moved as quickly as possible, maintaining the highest safety
    standards and
    compliance with legislation.
    "We are pleased that the Maui pipeline is back in service and that the last
    remaining
    customers have been brought back on line following this challenging and
    complex
    repair," he said.
    As at midday Sunday, the Critical Contingency Operator (CCO) declared that
    the Critical
    Contingency was over. Following this Critical Contingency incident there will
    be an
    incident report and a formal review, as required by the regulations.
    End CA:00215624 For:VCT    Type:GENERAL    Time:2011-10-31 09:00:07
    				
 