COB cobalt blue holdings limited

Ann: Half Year Accounts - December 2023, page-2

  1. 51 Posts.
    lightbulb Created with Sketch. 8
    The timeline stuck out again at me. They reference by June to have everything completed. They have 3 and half months left. Let's see.

    COB has developed a detailed Forward Work Plan to the commencement of construction. Between December 2023
    and June 2024 the plan is to:

     Complete testing of feedstock samples.
     Finalize the Refinery’s engineering and select engineering partner and construction firm.
     Secure binding feedstock contracts for the first 3–5 years of operation.
     Secure offtake contracts.
     Complete permit application studies; and
     Prepare financial information memorandum, identify sources of funds and close finance.
 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.
(20min delay)
Last
5.4¢
Change
-0.002(3.57%)
Mkt cap ! $24.02M
Open High Low Value Volume
5.5¢ 5.6¢ 5.4¢ $3.757K 68.29K

Buyers (Bids)

No. Vol. Price($)
3 201687 5.4¢
 

Sellers (Offers)

Price($) Vol. No.
5.6¢ 30000 1
View Market Depth
Last trade - 15.51pm 16/07/2025 (20 minute delay) ?
COB (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.