LIS li-s energy limited

LIS is planning a Phase 4 production facility with capacity of...

  1. 416 Posts.
    lightbulb Created with Sketch. 271
    LIS is planning a Phase 4 production facility with capacity of 500MWh+.

    Its 2MWh plant just commissioned cost $10 million and took about three years to build.

    On a pro-rata basis the Phase 4 facility would cost $2.5 billion.

    Who plausibly would fund this? How long would it take to construct? Who would be the customers?

    Because LIS itself has chosen to publicise this it follows that it should explain the basis upon which this could be funded, how long it would take to construct, potential sites, potential customers, potential battery metrics, etc, etc. If there is substance to this plan then LIS should share high level information about it. If there is insufficient substance to provide even high level information about the plan it would be wise not to mention it at all.
 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.
(20min delay)
Last
18.0¢
Change
0.010(5.88%)
Mkt cap ! $115.2M
Open High Low Value Volume
17.0¢ 18.5¢ 16.5¢ $186.5K 1.046M

Buyers (Bids)

No. Vol. Price($)
2 95266 17.5¢
 

Sellers (Offers)

Price($) Vol. No.
18.5¢ 798425 6
View Market Depth
Last trade - 15.59pm 28/07/2025 (20 minute delay) ?
LIS (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.