If the pond is filled with brine in Q1, why does it not start evaporating until the summer, ie Q4 24?
Given that the evaporation process takes at least 12 months, how can the project be in production by end of Q2 25?
- Forums
- ASX - By Stock
- Ann: HMW Phase 1 Construction Targets Maiden Production H1 2025
If the pond is filled with brine in Q1, why does it not start...
-
-
- There are more pages in this discussion • 16 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add GLN (ASX) to my watchlist
|
|||||
Last
16.0¢ |
Change
0.005(3.23%) |
Mkt cap ! $78.23M |
Open | High | Low | Value | Volume |
15.0¢ | 16.0¢ | 15.0¢ | $238.9K | 1.543M |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
4 | 302790 | 15.5¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
16.0¢ | 189198 | 6 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
4 | 302790 | 0.155 |
33 | 953404 | 0.150 |
11 | 460718 | 0.145 |
19 | 580796 | 0.140 |
7 | 483292 | 0.135 |
Price($) | Vol. | No. |
---|---|---|
0.160 | 189198 | 6 |
0.165 | 177000 | 6 |
0.170 | 150000 | 2 |
0.175 | 66000 | 2 |
0.180 | 125150 | 4 |
Last trade - 16.10pm 19/07/2024 (20 minute delay) ? |
Featured News
GLN (ASX) Chart |