He also said he would provide more details when he had it, he can't make things up just to be transparent and provide the answers you want. He also said exactly the reasons for the cost blow out.
Construction costs :
- lanour budgeted for $190/hr vs real costs $250/hr.
1000sqm of concrete is taking more people than budgeted.
We are also building a bigger plant now.
Listen to the presentations and Ann and your will hear most of your answers.
- Forums
- ASX - By Stock
- Ann: Investor Presentation BMO Conference
He also said he would provide more details when he had it, he...
-
-
- There are more pages in this discussion • 4 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add LTR (ASX) to my watchlist
(20min delay)
|
|||||
Last
$1.01 |
Change
0.015(1.52%) |
Mkt cap ! $2.437B |
Open | High | Low | Value | Volume |
97.0¢ | $1.04 | 96.5¢ | $12.25M | 12.21M |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
11 | 250234 | $1.00 |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
$1.01 | 51730 | 1 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
11 | 250234 | 1.000 |
10 | 200677 | 0.995 |
8 | 733988 | 0.990 |
2 | 74272 | 0.985 |
5 | 118874 | 0.980 |
Price($) | Vol. | No. |
---|---|---|
1.005 | 51730 | 1 |
1.010 | 50438 | 4 |
1.015 | 5550 | 2 |
1.020 | 40344 | 5 |
1.025 | 71000 | 3 |
Last trade - 16.10pm 19/07/2024 (20 minute delay) ? |
Featured News
LTR (ASX) Chart |