    Stage 1 - is to refurbish turbine hall 2 with the indicative installed power requirements of the base case process plant = 28 MW3 . 2 duty and 1 standby unit ▪ Stage 2 - is to refurbish turbine hall 1 with the additional indicative installed power requirements of process plant Stage 2 4 = 12.3 MW3 . 2 duty and 1 standby unit. ▪ Stage 1 and 2 combined will provide 40.3 MW guaranteed power output ▪ New HV power line and pylons to site ▪ 3 x ESIAs Approved ▪ RFTs for refurbishment in the market ▪ Studying to convert electrical excess renewable power to other uses, e.g., hydrogen for Fuel Cell Electric Vehicles (FCEV) use
 