No significant difference since December update, confirmation of completed milestones and delay in expected project energisation milestone.
Powerhouse cavern excavation completed as of this update (was expected by Q1 CY2024)
Wise's Dam completion completed as of this update (was expected by Q1 CY2024)
Aurumfield substation still on track for Q2 CY2024 completion
Project energisation delayed until Q1CY2025 (was Q4 CY2024)