No significant difference since December update, confirmation of completed milestones and delay in expected project energisation milestone.
Powerhouse cavern excavation completed as of this update (was expected by Q1 CY2024)
Wise's Dam completion completed as of this update (was expected by Q1 CY2024)
Aurumfield substation still on track for Q2 CY2024 completion
Project energisation delayed until Q1CY2025 (was Q4 CY2024)
- Forums
- ASX - By Stock
- Ann: Kidston Pumped Storage Hydro Project - Construction Update
No significant difference since December update, confirmation of...
-
- There are more pages in this discussion • 13 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add GNX (ASX) to my watchlist
(20min delay)
|
|||||
Last
26.5¢ |
Change
0.000(0.00%) |
Mkt cap ! $367.0M |
Open | High | Low | Value | Volume |
27.0¢ | 27.0¢ | 26.5¢ | $1.537M | 5.700M |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
33 | 31741663 | 26.5¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
27.0¢ | 15648906 | 150 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
25 | 22013998 | 0.265 |
22 | 31324152 | 0.260 |
1 | 22000 | 0.255 |
6 | 188000 | 0.250 |
1 | 5000 | 0.245 |
Price($) | Vol. | No. |
---|---|---|
0.270 | 15065799 | 145 |
0.275 | 2955245 | 37 |
0.280 | 323737 | 11 |
0.285 | 136061 | 5 |
0.290 | 32180 | 2 |
Last trade - 16.10pm 03/05/2024 (20 minute delay) ? |
|
|||||
Last
26.8¢ |
  |
Change
0.000 ( 0.93 %) |
|||
Open | High | Low | Volume | ||
26.8¢ | 27.0¢ | 26.8¢ | 416679 | ||
Last updated 15.59pm 03/05/2024 ? |
Featured News
GNX (ASX) Chart |