    Dependent on how they've structured their stages before Dry Commissioning they should already have completed

    Pre-commissioning checks - Initial Energisation - check HV & LV power to everything, check network comms to everything (fibre, Ethernet, serial) check Inputs & outputs of MCC modules.

    Dry Commissioning or No Load testing - bump motors to check direction (aligned before this), energise/check instrument installation/set up/confirm range/calibrate - loop checks, check logic via simulation (ie tank stop/start motor/valve levels), set dosing pump stroke, BOP usually up & going here ie service/instrument air, service water. Greenline drawings (as commissioned drawings).

    Wet Commissioning - everything is energised, simulated logic has been checked, so this is now where the rubber meets the road - system & process engineers start their functional & sequence testing in real life.

    Because they had a lot of the gear operating in those containers off site & have put it all through it's paces, the instrument settings, process times, temperatures, pressures ie operational parameters will be known & the plc/dcs logic will also be fairly robust.

    But 14 September they've reached mechanical completion & that's a major milestone.
 
watchlist Created with Sketch. Add LKE (ASX) to my watchlist
(20min delay)
Last
4.0¢
Change
0.002(5.26%)
Mkt cap ! $66.74M
Open High Low Value Volume
3.8¢ 4.1¢ 3.8¢ $296.0K 7.491M

Buyers (Bids)

No. Vol. Price($)
1 34999 4.0¢
 

Sellers (Offers)

Price($) Vol. No.
4.1¢ 348985 7
View Market Depth
Last trade - 16.10pm 12/07/2024 (20 minute delay) ?
LKE (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.