Salt Lake Potash Ltd (AIM:SO4, ASX:SO4, OTC:WHELF, LSE:SO4) is moving towards first SOP delivery as it works through Stage-4 of its load commissioning process for the Lake Way process plant near Wiluna in Western Australia.
The SO4 operations team, together with consultants from the plant designer and component manufacturers have been systematically working through the plant to ensure each unit is working within design parameters and the plant chemistry is established.
The company has also announced plans to implement a revised ramp-up strategy to enable more salts to precipitate before commencing continuous harvesting activities.
There is no anticipated impact on production levels in FY23 and beyond, with full production run-rate from primary salts still anticipated in the June 2022 quarter.