As part of the first phase of the project, Tenova’s scope of supply will include a magnesium oxide (MgO) plant, with spray roaster technology, with a production capacity of 300 kg/h. The demonstration plant will initially have capacity of 1,000 tonnes of magnesium (Mg) metal per year, and in the second stage
OK. So please correct me if I'm wrong but I'm not getting 1,000tpa unless the plant is open 14 hours a day.
So most companies close for Christmas break so I've used 50 weeks in my calculations.
300kg for 8 hours a day is 2.4t
2.4t for 5 days (1 working week) is 12t
12t times by 50 weeks is only 600tpa
As I said they will have to work 14 hours a day to make 1,000tpa
- Forums
- ASX - By Stock
- LMG
- Ann: Latrobe Magnesium awards spray roaster contract to Tenova
Ann: Latrobe Magnesium awards spray roaster contract to Tenova, page-13
-
- There are more pages in this discussion • 5 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add LMG (ASX) to my watchlist
(20min delay)
|
|||||
Last
4.7¢ |
Change
-0.001(2.08%) |
Mkt cap ! $103.0M |
Open | High | Low | Value | Volume |
4.6¢ | 4.8¢ | 4.6¢ | $49.09K | 1.047M |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
1 | 64217 | 4.6¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
4.7¢ | 90574 | 1 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
1 | 64217 | 0.046 |
6 | 696237 | 0.045 |
3 | 1255000 | 0.044 |
3 | 262120 | 0.043 |
5 | 1236738 | 0.042 |
Price($) | Vol. | No. |
---|---|---|
0.047 | 90574 | 1 |
0.048 | 213273 | 3 |
0.049 | 421200 | 4 |
0.050 | 73468 | 2 |
0.051 | 7000 | 1 |
Last trade - 16.10pm 12/07/2024 (20 minute delay) ? |
Featured News
TLX
Telix jumps 11.6% as US government indicates proposed medicare changes won't affect prostate cancer drug
SKS
SKS Technologies wins US$90M award to supply power to international hyperscale data centre in Melbourne
LMG (ASX) Chart |