Tinwins,
Iinitial MainRoads project claim included two separate elements;
1. Insurance claim relating to a number of damaging storm events during the project - now settled for 2.5 million.
2. A contractual claim relating to a variance between the amount of rock encountered in actual cuttings vs the expected amount - this is the ongoing matter as mentioned in the most recent update, with mediation set for some time in February.
The total combined amount of the two elements was forecast by BYL at roughly 9 million pre-tax. I don't ever recall BYL providing a breakdown of how each individual element contributed to this total so am unable to determine how that received 2.5 million for insurance contributes in actuality vs their initial estimates.
- Forums
- ASX - By Stock
- Ann: Main Roads Project Update
Tinwins, Iinitial MainRoads project claim included two separate...
-
- There are more pages in this discussion • 10 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add BYL (ASX) to my watchlist
Currently unlisted public company.
The Watchlist
MTL
MANTLE MINERALS LIMITED
Nick Poll, Executive Director
Nick Poll
Executive Director
SPONSORED BY The Market Online