Originally posted by jack2000:
↑
So reading the quarterly activities report it says the project will expect the first product during June. How feasible is this? From reading the other commissioning work/progress made it sounds like we won't get the first product till a bit later. The piping and electrical seem a bit of a stretch to finish within 2 months. A follow-on from this is that some equipment won't be commissionable until after the installations are made.
Expand
CEO is still indicating first sales in June. It looks like they haven’t run into any difficulties to date with the commissioning, and it’s all on track or ahead of schedule:https://twitter.com/tonyswiericzuk?s=21