    WHy would they need a "new crusher" (circuit ) ?
    My understanding is Most plants especially for open cut operations are built with considerable redundancy for the crusher circuit , ie only operate the crusher circuit for around 16 hours a day (while the mill operates 24/7 ) and have a fine ore bin down stream of the tertiary crusher that stores the crushed ore for a day or more so that gives even more redundancy
    The bottle neck tends to be the SAG or Ball mill in a plant as harder to do major overhauls on and more costly (replacing a ring gear or gear box or even liners and media ) and harder to replicate in a battery arrangement .
    In saying that maybe a different cyclone arrangement for the mill is appropriate to what you consider a possible issue ie reduce slurry density if less clay , or have a gravity circuit with IPJs .
    Maybe your supposition of new ore feed having a higher throughput would be best answered by getting a verification from the MD ?
    Last edited by plough: 29/04/23
 
watchlist Created with Sketch. Add BCN (ASX) to my watchlist
(20min delay)
Last
2.2¢
Change
-0.004(15.4%)
Mkt cap ! $82.64M
Open High Low Value Volume
2.4¢ 2.4¢ 2.2¢ $178.4K 7.785M

Buyers (Bids)

No. Vol. Price($)
14 4916787 2.2¢
 

Sellers (Offers)

Price($) Vol. No.
2.3¢ 1124630 2
View Market Depth
Last trade - 16.10pm 18/09/2024 (20 minute delay) ?
BCN (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.