    Permit granted 19-Nov 2009
    Extension of Duration (Exploration) granted 15-Nov-2013

    60 Months :

    Stage 1b
    Key Committed - 3(b) either: (i) notify the chief executive in writing of the permit holder?s commitment to carry out the additional seismic acquisition identified in condition 4(b) below; and (ii) relinquish 25% of the original permit area; or (iii) relinquish 50% of the original permit ...

    Stage 1b - Key Committed - 3(a) acquire and process a minimum of 310 square kilometres of 3D seismic data;
 