    From what I researched, construction started around June 18, so 2.5 years to complete it looks good.

    Delays to start btw 2005 and 2008 was because they had some major permitting issues which resulted in long delays with the PNG government.

    Also, Ramu was a greenfields site, with zero infrastructure in place, they had to build port facilities, all infrastructure meaning they had a long lead time on early works, before they could even start on the mine/processing plant

    http://pg2.mofcom.gov.cn/article/supplydemandofchina/cooperation/200509/20050900484583.shtml

    file:///C:/Users/bovef/Downloads/Ramu_Construction.pdf
 
watchlist Created with Sketch. Add SRL (ASX) to my watchlist
(20min delay)
Last
47.0¢
Change
0.020(4.44%)
Mkt cap ! $42.40M
Open High Low Value Volume
45.0¢ 47.0¢ 45.0¢ $713 1.568K

Buyers (Bids)

No. Vol. Price($)
2 1818 45.0¢
 

Sellers (Offers)

Price($) Vol. No.
51.0¢ 1500 1
View Market Depth
Last trade - 14.10pm 09/09/2024 (20 minute delay) ?
SRL (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.