I have been following through on this line of thought, and can now confirm a permit to drill was issued by AOGCC for the Merlin 1 well last year, approved on 26/02/2021, some 28 days after Federal approval was given by the BLM on 29/01/2021.
It is a little more than the 15 working days AOGCC specify in their process flow, but allowing for weekends quite a close alignment.
On this basis this final Merlin 2 drill permit would be due 3/3/22, which again aligns with the early March spud date given by the company
http://aogweb.state.ak.us/Drilling
Apologies in advance for the tiny print, but the only way I could get enough detail
- Forums
- ASX - By Stock
- 88E
- Ann: Merlin-2 Operations Update
Ann: Merlin-2 Operations Update, page-212
Featured News
Add 88E (ASX) to my watchlist
(20min delay)
|
|||||
Last
0.3¢ |
Change
0.001(25.0%) |
Mkt cap ! $72.23M |
Open | High | Low | Value | Volume |
0.2¢ | 0.3¢ | 0.2¢ | $13.94K | 5.647M |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
481 | 942252809 | 0.2¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
0.3¢ | 392511647 | 69 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
481 | 942252809 | 0.002 |
116 | 607791048 | 0.001 |
0 | 0 | 0.000 |
0 | 0 | 0.000 |
0 | 0 | 0.000 |
Price($) | Vol. | No. |
---|---|---|
0.003 | 392512095 | 69 |
0.004 | 510569737 | 201 |
0.005 | 237011915 | 97 |
0.006 | 77938535 | 70 |
0.007 | 235781401 | 41 |
Last trade - 13.23pm 28/05/2024 (20 minute delay) ? |
|
|||||
Last
0.3¢ |
  |
Change
0.001 ( 15.4 %) |
|||
Open | High | Low | Volume | ||
0.3¢ | 0.3¢ | 0.3¢ | 13778499 | ||
Last updated 13.48pm 28/05/2024 ? |
Featured News
88E (ASX) Chart |