Spinifex and others asking about timelines to commemce OP mining & Coyote processing should refer to Slide 11 (page 12) of presentation released to ASX today. Excerpt below:
Old Pirate Critical Path - Updated Schedule
12 week (*) period to commissioning
Weeks 1 to 4
Site Establishment
Access road grading
Pre-strip
Weeks 4 to 8
Mining & stockpiling of first ore
Coyote Plant refurbishment
Weeks 8 to 12
Coyote Plant refurbishment completion
Commissioning with 10,000 tonne parcel
* Subject to change dependent on access during wet season.
My Comment: ** If the only thing that delays the above timeline is the wet I'll be very pleasantly surprised ....
- Forums
- ASX - By Stock
- Ann: Mining Contractor Selected & Mobilisation Commencing
Spinifex and others asking about timelines to commemce OP mining...
-
-
- There are more pages in this discussion • 1 more message in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add PRX (ASX) to my watchlist
(20min delay)
|
|||||
Last
0.2¢ |
Change
-0.001(33.3%) |
Mkt cap ! $6.350M |
Open | High | Low | Value | Volume |
0.3¢ | 0.3¢ | 0.2¢ | $6.473K | 2.224M |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
23 | 51510682 | 0.2¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
0.3¢ | 87637716 | 45 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
23 | 51510682 | 0.002 |
67 | 152786436 | 0.001 |
0 | 0 | 0.000 |
0 | 0 | 0.000 |
0 | 0 | 0.000 |
Price($) | Vol. | No. |
---|---|---|
0.003 | 86637716 | 44 |
0.004 | 15954506 | 16 |
0.005 | 2867123 | 4 |
0.006 | 2600001 | 4 |
0.007 | 1717000 | 3 |
Last trade - 16.10pm 07/11/2024 (20 minute delay) ? |
Featured News
PRX (ASX) Chart |