NZR 0.00% 0.0¢ the new zealand refining company limited

Ann: MONTHLY: NZR: Business Update-Throughput and

  1. lightbulb Created with Sketch. 2
    • Release Date: 27/11/13 12:25
    • Summary: MONTHLY: NZR: Business Update-Throughput and Margin Report(Sept-Oct 2013)
    • Price Sensitive: No
    • Download Document  3.98KB
    					NZR
    27/11/2013 10:25
    MONTHLY
    
    REL: 1025 HRS The New Zealand Refining Company Limited
    
    MONTHLY: NZR: Business Update-Throughput and Margin Report(Sept-Oct 2013)
    
    The Processing Fee earned for the period September to October 2013 was NZD
    16.6 million, generated from a throughput of 6.7 million barrels.
    
    The average Gross Refinery Margin 1) (GRM) for the two month period was USD
    2.91 per barrel and the average exchange rate was USD/NZD 0.83.
    
    Singapore complex margins remained negative throughout the two-month period,
    and this affected refining margins across the refining industry worldwide.
    
    A planned three-week shutdown, to regenerate the Platformer catalyst and to
    perform maintenance on a crude distiller and a desulphurisation unit,
    commenced in late October and was completed on time.  The shutdown reduced
    throughput volume by around 1.5 million barrels, mostly in the
    November/December period.  The Company remains on track to achieve a
    throughput of close to 41 million barrels during 2013.
    
    Appendix I shows further information on throughput, margin and refining
    income.  The Gross Refining Margin for the year to date is USD 5.03 per
    barrel and the exchange rate USD/NZD 0.82.  A five year history of
    Throughput, Margins and Processing Fees is attached as Appendix II and can
    also be found on the company's website:  www.refiningnz.com
    
    CCR Project - Te Mahi Hou
    
    Te Mahi Hou is progressing to plan with the achievement of two milestones -
    the pour of the concrete foundation for the CCR unit and the delivery of the
    main CCR reactor - during the reporting period.
    
    The CCR foundation laid on the 9th of November required around 2750 cubic
    metres of concrete.  The delivery of 550 truckloads over a 16 hour period
    made this one of the largest continuous concrete pours undertaken in New
    Zealand.  A week later the 52 metre long CCR reactor weighing 172 tonnes was
    delivered to Northport from Mumbai, India.  This is the first major CCR piece
    to be delivered to the refinery.
    
    The $365 million project, due to be commissioned in December 2015, will
    increase the Company's processing capability by around 3 million barrels per
    year and deliver an estimated uplift in the Gross Refiners Margin of around
    USD1.10 per barrel, through improved energy performance and yields.  To date,
    $165 million has been spent on the project, excluding Front End Engineering
    and Design and capitalised interest.
    
    Hydro-cracker Projects
    
    Planning for a month-long maintenance shutdown of the hydro-cracker next
    March, is well underway.  At that time, several margin enhancing and other
    initiatives will be completed. The Company remains on track to deliver in
    2014 the estimated USD0.66 per barrel uplift in Gross Refiners Margin through
    these initiatives and the estimated $4 million cost savings versus 2012
    actual expenditures.  Detail of these projects was included in the August
    2013 presentation to analysts which can also be found on the company's
    web-site.  The capital spend through the hydro-cracker shutdown, including
    the purchase of fresh hydro-cracking catalyst is around $55 million.
    
    Looking ahead
    
    The scope and timing of the hydrocracker shutdown, coupled with the continued
    weakness in Refiners Margins, means that it is likely that the company's
    borrowings will "peak" in 2014 at around $80-$120 million higher than
    originally estimated at the time of the Te Mahi Hou investment case.
    (Current borrowings amount to around $170 million).  As a prudent step, the
    Board of Directors have resolved to supplement the $300m banking facilities,
    that were put in place when Te Mahi Hou was approved, with longer term core
    debt of $150 million.  The Company is currently in positive discussions with
    its bankers to put this longer term core debt into place and a further
    announcement will be made when these arrangements are complete.
    
    ENDS
    For further information contact:
    Greg McNeill
    Communications and External Affairs Manager
    Refining NZ
    T: 09 432 82311
    M: 021 873 623
    E: [email protected]
    End CA:00244356 For:NZR    Type:MONTHLY    Time:2013-11-27 10:25:24
    				
 
watchlist Created with Sketch. Add NZR (NZSX) to my watchlist

Currently unlisted public company.

arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.