    Based on my gut feel with what still needs to happen i feel we wont be drilling until approx this time next year based on the following estimated timeline...

    PPSA within the next 3 months

    JV within the next 6 months. I highly doubt this happens shortly after PPSA. PPSA would need JV partner solicitor review, contract then finalised with both parties solicitor review, this will take some time to finalise.

    Service provider contracts signed & balance of long lead items ordered. This should happen shortly after JV contracts are unconditional. They take 90 days to mobilise

    Rig move & set up.... possibly 6-8 weeks.

    They are not going to start drilling the wet season which ends at the end of March so based on the above best case scenario is start of April next year IMO.
 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.
(20min delay)
Last
5.0¢
Change
0.001(2.04%)
Mkt cap ! $80.17M
Open High Low Value Volume
5.0¢ 5.2¢ 4.8¢ $228.7K 4.596M

Buyers (Bids)

No. Vol. Price($)
1 290000 4.9¢
 

Sellers (Offers)

Price($) Vol. No.
5.0¢ 119195 3
View Market Depth
Last trade - 16.10pm 27/06/2025 (20 minute delay) ?
IVZ (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.