if correct, 3 month delay...
some saying current utilisation is 50%
company aiming for 85% with +2 filter presses
that's +35%
delay costs 3 months x 35%
about 1 month of production is lost due to a 3 month delay.
then 7 months later, hoping for the super whopper to allow 100% utilisation.
why the horsesheet they call it standby???
anyway, 100 minus 85 is 15%
7 months x 15% is about 100% or 1 full month of lost productivity.
so, delays do cost but don't cost much overall.
once problem identifed, solution found, and begin implementing, the cost is minimised.
most damage has already been done from the start of commissioning.
- Forums
- ASX - By Stock
- Ann: New tailing filter press ordered. Shipment update.
AUQ
alara resources limited
Add to My Watchlist
6.06%
!
3.5¢

if correct, 3 month delay...some saying current utilisation is...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.
|
|||||
Last
3.5¢ |
Change
0.002(6.06%) |
Mkt cap ! $28.10M |
Open | High | Low | Value | Volume |
3.5¢ | 3.6¢ | 3.5¢ | $3.706K | 105.7K |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
2 | 35442 | 3.4¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
3.5¢ | 372546 | 2 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
1 | 6060 | 0.034 |
2 | 151181 | 0.033 |
2 | 62414 | 0.032 |
1 | 200000 | 0.031 |
4 | 1317000 | 0.030 |
Price($) | Vol. | No. |
---|---|---|
0.035 | 372546 | 2 |
0.036 | 497323 | 1 |
0.037 | 515000 | 2 |
0.038 | 600000 | 2 |
0.040 | 765418 | 3 |
Last trade - 15.46pm 28/07/2025 (20 minute delay) ? |
Featured News
AUQ (ASX) Chart |