    Early Works Program

    Whilst it has been noted that AVZ is currently going to the market to invite tenders for various design
    and construction works, planning of the Early Works Program continues unabated. The current Colline
    Manono camp site, catering for up to 55 workers, will be expanded during the year to accommodate an
    extra 100 construction personnel during the expected 12-18 months required to build the MLTO plant
    and associated infrastructure. Other works such as the development of modern well drained, access
    roads to and from the plant site will also be completed as part of this program. This will facilitate an
    immediate start for the construction crew when they arrive in Manono.

    The Early Works Program also includes the building of the site office and the fabrication workshop on
    the site, allowing the commencement of the Apprenticeship Training Program, designed to select
    candidates for training and potential future employment on the site.
 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.

Currently unlisted public company.

arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.