- 6 tonnes produced in June (461 tonnes of skarn and scat processed for this amount)
- Preferred crusher contractor fell through due to operational requirements (why did we even do a crushing trial if we couldn't agree upon time frames?)
- Buying second hand crushing machine which will take 3-4 weeks to be refurbished (not including the time it will take to be delivered to Granville, it is in Tasmania though)
- Strategic review on Granville, decision to focus on higher mine grade and recovery which means slower production rates
Cost estimates are going to be higher now and the whole purpose of this production schedule was to fund Taronga, it literally tells me Taronga is going to be delayed by a year at least. Not to mention production is pretty much at a standstill until Mid August.
Good to know we are still a leaky ship also.
- Forums
- ASX - By Stock
- Ann: Operations and Development Update
- 6 tonnes produced in June (461 tonnes of skarn and scat...
-
- There are more pages in this discussion • 221 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add C7A (ASX) to my watchlist
(20min delay)
|
|||||
Last
1.0¢ |
Change
0.000(0.00%) |
Mkt cap ! $2.501M |
Open | High | Low | Value | Volume |
1.0¢ | 1.0¢ | 1.0¢ | $115 | 11.46K |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
3 | 1713070 | 0.9¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
1.0¢ | 488766 | 2 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
3 | 1713070 | 0.009 |
3 | 573919 | 0.008 |
4 | 992855 | 0.007 |
4 | 582661 | 0.006 |
2 | 1500000 | 0.005 |
Price($) | Vol. | No. |
---|---|---|
0.010 | 488766 | 2 |
0.011 | 740905 | 2 |
0.012 | 1081280 | 4 |
0.013 | 944662 | 2 |
0.015 | 66732 | 1 |
Last trade - 14.30pm 27/09/2024 (20 minute delay) ? |
Featured News
C7A (ASX) Chart |