    88 Energy Limited
    Project Icewine Operations Update
    88 Energy Limited (“88 Energy”, “the Company”, “Operator”) (ASX, AIM: 88E) is pleased to provide
    an update on Project Icewine, located onshore North Slope of Alaska.
    Highlights
    • Currently flowing back naturally on 8/64 choke at ~55 barrels per day frac fluid
    • Minor hydrocarbon indications via flow rate of 2-4mcf of gas per day, with a maximum rate of
    8mcf of gas per day
    Icewine#2 Operations Update
    The Icewine#2 well was shut-in on 10th July to allow for imbibition and pressure build up to occur within
    the HRZ shale. Flow testing re-commenced on 31st August at 10:26 (AK time), and is ongoing. Results
    since flow testing recommenced are summarised below.
    The Icewine#2 well is located on the North Slope of Alaska (ADL 392301). 88 Energy Ltd (via its
    wholly owned subsidiary, Accumulate Energy Alaska, Inc) has a 77.55% working interest in the well.
    The well was stimulated in two stages over a gross 128 foot vertical interval in the HRZ shale
    formation, from 10,957-11,085ft TVD, using a slickwater treatment comprising 27,837 barrels of fluid
    and 1,034,838 pounds of proppant.
    The well was initially flowed back on a 6/64 inch choke and was reduced to a 4/64 inch choke after 26
    hours to maintain pressure. Approximately 370 barrels of frac fluid had been recovered as at 1730 on
    3rd September (AK time) at an average rate of 100 barrels per day. The choke was subsequently
    stepped up to 8/64 inch at 1800 10th September (AK time) as the overall declining pressure gradient
    versus time improved, indicating potential pressure support. To date, the cumulative amount of
    stimulation fluid produced from both testing periods is 5,277 barrels, 19.0% of fluids injected.
    Wellhead pressure built to ~3,500psi during shut-in and has dropped to 106psi since flowback
    commenced and is now declining very slowly with a relatively constant flowback rate of 55 barrels per
    day. At 0930 9th September (AK time), a decision was made to run the flowback through the test
    separator due to minor gas indications being evident. To date the rate of flow has been unstabilised
    at between 2 and 4 mcf per day made up of 76% hydrocarbons, 20% atmospheric gases and 4%
    inorganics. The produced hydrocarbons comprise 93% methane with 7% heavier fractions.
    The current flowback procedure remains early stage with only 19.0% of the frac fluid retrieved. The
    gas observed so far is not considered representative of the potential rate or composition of
    hydrocarbon in the reservoir. It is interpreted that additional frac fluid needs to be removed in order to
    achieve a representative result. A decision will be made on the most appropriate strategy to
    accomplish this within the next two weeks.
    Yours faithfully
    Dave Wall
    www.
 
watchlist Created with Sketch. Add 88E (ASX) to my watchlist
(20min delay)
Last
0.2¢
Change
-0.001(33.3%)
Mkt cap ! $57.78M
Open High Low Value Volume
0.3¢ 0.3¢ 0.2¢ $13.04K 4.415M

Buyers (Bids)

No. Vol. Price($)
607 876949277 0.2¢
 

Sellers (Offers)

Price($) Vol. No.
0.3¢ 638654565 135
View Market Depth
Last trade - 11.55am 21/06/2024 (20 minute delay) ?
88E (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.