Additional Machinery for Recovery Plan
The following additional mining equipment provided by MACA under its Mining Contract with Beadell has arrived and is arriving on site:
• 40T Volvo dump truck x 5, arrived 13th April
• 9150 Liebherr (150 ton excavator), arrived 30th May
• 16M grader x 2, arrived 30th May
• 580 Front end loader ordered (in-country) ETA early June
• F9 Drill and Blast rig x 2 ETA early June
• EC700 Volvo 70t excavator, ETA early June
• D9 Dozer, ETA mid-July
• 777G Caterpillar dump truck x 3 ETA 7th August
• 5150 Drill & Blast Rig x 2 - ETA 30th August
Additional external hire of all earthmoving equipment for the mining of Duckhead open pit cutback due onsite late June.
most machinery arrived late last month,lets wait and see.