    1. I assume this GOR sample is the same sample that is talked about in the last announcement?

    "Sample analysis will take place in a lab over the next four to six weeks to allow for detailed characterisation of the hydrocarbon composition and phase in the reservoir."

    I have the Sample results coming out a lot later than the 23rd - 4th July dates you have, as the announcement states 4-6 weeks for analysis from the time the samples were taken.

    2. It seems the 8-14 days that I noted, is about right for the clean-up/sample taking duration. Cheers for the June 13th announcement quote.

    3. I have just given say 10 days for the Upper Zone clean Up. Then 10 days for the Co-mingled clean up, then 2 weeks for the Production test/choke release. Total of 34 days. This takes us to around the 24th July for Flow Results. I assume you have been more optimistic than me on the clean-up time.

    4. I am not clear on how long a production test will take to get the optimal flow rate. Dave has just said 'several weeks' and I don't have anything more specific than that - any ideas on the sort of timescale for this? I have counted 2 weeks.
 