COE 2.22% 23.0¢ cooper energy limited

Ann: Orbost Improvement Project Update, page-23

  1. 8,512 Posts.
    lightbulb Created with Sketch. 2746
    yep, I don't profess to know the answer.
    But what is clear, is that the installation of the polisher unit has extended the higher production rate, and reduced the number of cleans of the absorbers.

    Untitled.jpg

    what seems to be bit confusing is the claim that the prod rate has averaged 59tjd when both absorbers were in operation. That is not the number that counts. what does count, is the average daily production. We could have 2 days at 100tjd, and then 28 days shut down! Looks good for 2 days, but trouble the rest of month.

    what has changed is that it seems we had about 10 days of prod at high 50's to 60's, then absorber clean ---> it was 2 days at 31tjd (which is one absorber operating) then straight back into 61tjd yesterday.

    So on average, I think production will be up with this new polisher.

    We need to have a look over at least a couple of months to see what a consistent rate is produced.
 
watchlist Created with Sketch. Add COE (ASX) to my watchlist
(20min delay)
Last
23.0¢
Change
0.005(2.22%)
Mkt cap ! $607.2M
Open High Low Value Volume
22.5¢ 23.0¢ 22.5¢ $183.4K 810.0K

Buyers (Bids)

No. Vol. Price($)
2 491238 22.5¢
 

Sellers (Offers)

Price($) Vol. No.
23.0¢ 644269 13
View Market Depth
Last trade - 16.10pm 24/05/2024 (20 minute delay) ?
Last
22.5¢
  Change
0.005 ( 0.04 %)
Open High Low Volume
22.5¢ 22.8¢ 22.5¢ 131657
Last updated 15.57pm 24/05/2024 ?
COE (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.