QGC queensland gas company limited

Highlights:�� Berwyndale South # 60 recorded gas...

  1. 430 Posts.
    Highlights:
    �� Berwyndale South # 60 recorded gas flows of between 1.3 and 1.4 mmcfd during a six hour
    test on Easter Monday. Like other high-performing wells at the field (Wells # 16 and # 18),
    the well has been shut in to preserve the gas for sale.
    �� All 25 production wells for the CS Energy contract have been drilled; 23 of those wells are
    ready for production and 20 have undergone production testing.
    �� Seven of the 25 wells have been completed as free-flowing wells, resulting in lower capital
    and operating costs at the well head and an overall improvement in project economics.
    �� Australian Pipeline Trust has completed the physical connection into the Roma to Brisbane
    Gas Pipeline (RBP) and the export pipeline is complete, tested, dry and ready for first gas
    sales.
    �� Commissioning of the field compressor station is underway with all three screw
    compressors successfully tested.
    �� The trunk line for the gas gathering system has been pressure-tested and purged with gas.
 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.

Currently unlisted public company.

arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.