Highlights:
Berwyndale South # 60 recorded gas flows of between 1.3 and 1.4 mmcfd during a six hour
test on Easter Monday. Like other high-performing wells at the field (Wells # 16 and # 18),
the well has been shut in to preserve the gas for sale.
All 25 production wells for the CS Energy contract have been drilled; 23 of those wells are
ready for production and 20 have undergone production testing.
Seven of the 25 wells have been completed as free-flowing wells, resulting in lower capital
and operating costs at the well head and an overall improvement in project economics.
Australian Pipeline Trust has completed the physical connection into the Roma to Brisbane
Gas Pipeline (RBP) and the export pipeline is complete, tested, dry and ready for first gas
sales.
Commissioning of the field compressor station is underway with all three screw
compressors successfully tested.
The trunk line for the gas gathering system has been pressure-tested and purged with gas.