ASX ANNOUNCEMENT ASX CODE: CTP 12 December 2011 TO: The Manager,...

  1. 1,705 Posts.
    lightbulb Created with Sketch. 3
    ASX ANNOUNCEMENT ASX CODE: CTP
    12 December 2011
    TO: The Manager, Company Announcements ASX Limited
    CONTACT: John Heugh +61 8 9474 1444
    HORIZONTAL WELLBORE TO TEST SURPRISE-1
    ? Lateral completion of up to 700m planned to test Lower Stairway
    Sandstone
    ? 17m of gross hydrocarbon column interpreted in Lower Stairway
    Sandstone
    ? Permeabilities up to 420 Millidarcys (mD)
    Central Petroleum Limited (ASX:CTP) (“Central” or the “Company”), has pleasure in
    announcing that interpretation of electric logs, cuttings sampling, gas chromatography
    and coring to date has indicated a possible gross oil column in the Lower Stairway
    Sandstone of up to c.17m, with permeabilities ranging up to 420 Millidarcys measured
    in a 9m cored zone. Smaller hydrocarbon zones up to c.1m in the Middle Stairway
    Sandstone and up to c.2m in the Top Pacoota Sandstone have also been interpreted.
    The presence of hydrocarbons and elevated organic material in sections of the Horn
    Valley Siltstone has also been interpreted and samples taken will be studied for
    unconventional shale oil/gas potential.
    Only the hydrocarbon zones in the Lower Stairway and the Middle Stairway are thought
    to have flow potential using conventional production techniques (ie not using hydraulic
    fracturing). It is planned to complete a seismic check shot survey over the section from
    surface to the Total Depth reached to date of 2,732m RKB before running 7 inch
    casing. It is then planned to mill a window in the casing above the Middle Stairway
    Sandstone before directionally drilling a 6 inch sidetrack to intersect and drill a
    horizontal wellbore of up to c.700m through the interpreted Lower Stairway oil column.
    The angle build and horizontal wellbore sections will utilise a gamma ray tool for geo
    steering, a modern technique commonly used to ensure accurate placement of the well
    bore within the potential production reservoir. Underbalanced drilling techniques to
    minimise formation damage and maximize production potential are planned together
    with a “barefoot” (uncased open hole) for completion, testing and possible production.
    Mr Dalton Hallgren, the Company’s recently appointed Chief Operating Officer and well
    qualified directional and horizontal Drilling Engineer, will take personal charge at the
    well site of the horizontal drilling and testing programme expected to commence by late
    this week following the setting of casing.
    “The results thus far from the drilling and logging of Surprise-1 are such that a
    horizontal wellbore test of the Lower Stairway Sandstone is considered appropriate”
    said Mr John Heugh, the Managing Director this morning. “Movable oil has yet to be
    proved but the Company is optimistic and believes that a horizontal wellbore offers the
    best possible chance for oil flow to surface by accessing a much longer sandstone
    section than is possible via a vertical wellbore.” The Surprise ST-1 well has reached a Total Depth of 2,732m RKB within the Pacoota
    Sandstone in 8.5 inch hole size. These preliminary results are all subject to review and
    revision as more data is acquired. Further updates will be released as significant
    results come to hand. The revised programme is subject to the approval of the
    Northern Territory Department of Resources.
    Given the timing of these operations, a further extension of the Share Purchase Plan is
    being considered. Any conclusions will be the subject of a further announcement.
    Return mud-stream Surprise-1 showing free gas breakout and oil slicks in 8.9 ppg/1.07
    SG mud (slightly overweight)-viewed on circulation after electric logging runs before
    planned check shot survey. Gas composition C1/C2/C4/C5 percentages 41 /24/ 20/ 11/ 4
    respectively. Note : No conclusions can be definitively made on the capability of the
    well to flow oil to surface from these indications but they are regarded as positive
    indicators rather than negative indicators.
    John Heugh
 
watchlist Created with Sketch. Add CTP (ASX) to my watchlist
(20min delay)
Last
5.3¢
Change
0.000(0.00%)
Mkt cap ! $39.22M
Open High Low Value Volume
5.3¢ 5.4¢ 5.3¢ $52.12K 978.8K

Buyers (Bids)

No. Vol. Price($)
1 454057 5.3¢
 

Sellers (Offers)

Price($) Vol. No.
5.4¢ 46397 1
View Market Depth
Last trade - 16.10pm 28/06/2024 (20 minute delay) ?
CTP (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.