Golden State Resources Limited has run 13⅜” casing to 3,806’. The well is
currently circulating through the stage tool waiting for the stage 1 cement
to set, prior to cementing the upper stage. The well is expected to drill out
of casing once the second stage cement has set.
Operations on the Paradox Basin #2 well are proceeding ahead of schedule. Unit Rig 234
drilled to the surface casing point at 3,806’ in approximately 7 days and has run the 13 ⅜”
casing and set the first stage of two stages of cement. The second stage cement is
expected to be completed today before continuing to air hammer drill in 12 ½“ hole to
approximately 6,000’ before switching to a conventional mud system and rotary drilling.
Current operations are eight days ahead of schedule and are 16 days ahead of the
equivalent operations in the Paradox Basin #1 discovery well. Rig 234 has performed
reliably through‐out operations with minor lost time due to a minor electrical problem.
Minor time losses have also been attributed to reliability of the air hammer.
- Forums
- ASX - By Stock
- GDN
- ann out
ann out
Featured News
Add GDN (ASX) to my watchlist
Currently unlisted public company.
The Watchlist
FHE
FRONTIER ENERGY LIMITED
Adam Kiley, CEO
Adam Kiley
CEO
SPONSORED BY The Market Online