On the ground water fauna thing, yes, the update from OZL says there is a potential for 12 months plus delay for environmental approval. The worried me for a day, but hey, OZL have thrown an additional $10m at the project and they did that having assessed the potential for delays/dewatering etc. That $10m derisks my investment in CZI.