Yes ashc36, thanks , just released on market now.
Must be this part “ early commission underground on the way “
Underground – early commissioning underway
• Initial target 18,000t of ore left behind
• 234kt of Inferred Resource at 0.95% based on 4 veins
• Open at depth with increasing tenor
Current work programme
• Entrances cleared with safe access
• Installation of main dewatering pumping station
• Cleaning works and removal of rock waste
• Construction of water drainage channels system
• Sealing redundant stopes and ventilation raises
• Evaluation of geotechnical stability and reinstallation of ground support
• Electrification completed for stage 1