    KEY POINTS

    • Site preparations at the Company’s flagship Lance Uranium Project continue to progresstowards recommencement of production operations in December 2024

    • The Lance Central Processing Plant (“CPP”) expansion construction contract is beingtransitioned to a fixed cost basis

    • The final CPP capital cost is projected to be US$9.5M higher than previous estimate

    • PEN maintained a cash balance of US$68M at 31 October 2024 and is funded well beyond firstproduction

    • Working capital and debt facility funding discussions are advanced

    • CY2025 ramp-up production profile revised downward to 600,000 lbs U3O 8 reflecting currentstatus of projectwide development (previous range of 700,000 to 900,000 lbs)

    • Overall CY2026 and CY2027 production projections not materially impacted by early ramp-upstage delays

    • Kendrick Area permitting process advances to final review and approval stage

    • Managing Director, Wayne Heili has indicated his intention to resign from the MD/CEO role in2025. An executive search process has been commenced for a new MD.

    • The Company is currently advancing Senior Management and Board succession with a COOappointment imminent

 