re: Ann: Penumbra Mine Equipment Delivered fo...
yes chris it was the aug ann. i quoted the figures from.
there % complete still doesnt add up to me with there deadlines as per my previous post.
"During July, the declines encountered and developed through the previously identified dolerite dyke. Following the development through the dyke, the decline angle was changed from 5.10 to 8.00 at 205m (planned at 230m). As a result, the decline will now reach first coal 16m earlier, with each decline now planned to be 374m in length (previously planned at 390m)."