    Currently the Penumbra Coal Project is 38.2% complete with a total forecast cost to complete of ZAR328m (approx. A$38.5m), and is substantially on budget.
    PROJECT SCHEDULE (As at 22 June 2012)
    % Complete
    Engineering
    78.3%
    Procurement
    49.9%
    Manufacture and Delivery
    10.6%
    Construction
    31.9%
    Mining
    23.9%
    Overall Project
    38.2%
 