re: Ann: Pictorial 16 - Comprehensive Project... A couple of highlights :
"Current mining costs = $1.90 per tonne.
This compares extremely favourably with the projected $3.40 per tonne from pre-development mining studies, as prepared by independent consultants."
"The Company plans to eventually increase the current dump-truck fleet further, to facilitate mining operations on a 12 hour, 5 day week shift, which will produce sufficient feed ore to meet the Process Plant’s 24 hour shift requirements."