Key Highlights
? Underground Probable Ore Reserve 2.97 million tonnes @ 3.61 g/t for 344,500 ounces
? Total recovered ounces 310,000 ounces
? Cash Costs US$714 per ounce
? AISC US$825 per ounce
? Initial Life of Mine (“LOM”) 7 - 8 years
? Gross revenue US$347 million
? Pre-production capital (Capex and Opex) US$18.1 million
? LOM Sustaining Capex US$34.3 million
? Pre-tax NPV5% US$49 million
? Payback period 4 years
? Pre-tax IRR 30%
? PFS study accuracy +25%
- Forums
- ASX - By Stock
- Ann: Positive Urucum Underground Pre-Feasibility Study
Key Highlights ? Underground Probable Ore Reserve 2.97 million...
-
- There are more pages in this discussion • 28 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
GML
Gateway Mining sells WA Eastern Montague gold project to Brightstar for $14M – half of that in shares
MND
Albemarle lithium downsize burns $200M hole in Monadelphous's pocket as latter's contracts terminated