Reasonable numbers revenue and opex numbers @Bayhunter, but the capital cost won't be that low, I think. The best answer I've gotten so far is "under US$100m". US$50m is indeed under US$100m, but I think it is likely the number is closer to US$90m.
Remembering that the plant is twice the size of what was considered in the PFS, and they will be developing the mine instead of buying ore, and the capital cost is higher than the PFS would have considered.
The plant also won't be operating at 5,600tpa from day one, and you need to factor in the ~15 month or so build time for P1 if you're calculating payback period. If we said it takes a full year to ramp up to 5,600tpa, then we're probably talking about 3-3.5 years to pay back the capital investment, from the time construction starts.
Not quite as good as a payback period of 1, but still pretty damn good.
Cheers
- Forums
- ASX - By Stock
- LPD
- Ann: Production Schedule guides to significant By-Product Volumes
Ann: Production Schedule guides to significant By-Product Volumes, page-72
-
- There are more pages in this discussion • 5 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add LPD (ASX) to my watchlist
|
|||||
Last
0.3¢ |
Change
0.001(20.0%) |
Mkt cap ! $25.76M |
Open | High | Low | Value | Volume |
0.3¢ | 0.3¢ | 0.3¢ | $1.606K | 569.1K |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
180 | 206882564 | 0.2¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
0.3¢ | 122521290 | 56 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
180 | 206882564 | 0.002 |
43 | 183161088 | 0.001 |
0 | 0 | 0.000 |
0 | 0 | 0.000 |
0 | 0 | 0.000 |
Price($) | Vol. | No. |
---|---|---|
0.003 | 92521290 | 55 |
0.004 | 42199643 | 48 |
0.005 | 11857316 | 14 |
0.006 | 9138260 | 14 |
0.007 | 4963897 | 6 |
Last trade - 16.10pm 04/07/2024 (20 minute delay) ? |
Featured News
LPD (ASX) Chart |