    Hard to gauge overruns without completing the project. Most are incurred towards the end of a build, especially for something like this where the earthworks, lining etc are fairly straightforward tasks for contractors. Not exactly a whole lot of project management or complexity involved. The plant was always going to be the test.

    No doubt there would be added costs thrown in because of the stop start approach but as you say that was unavoidable given position they got themselves in.

    Now that authium is building the plant and financing task has been handballed to them, they dictate the timeline. Galan couldn't finance the build with a project behind it, authium will with no assets of value to secure the debt. Apparently it's in the bag? I didn't see any timelines set on authium, I might have missed it but you'd usually like to see some sort of drop dead clause in these sort of things to avoid being strung along indefinitely.

    Aimo
 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.
(20min delay)
Last
9.3¢
Change
-0.001(1.06%)
Mkt cap ! $89.09M
Open High Low Value Volume
9.6¢ 9.7¢ 9.3¢ $260.7K 2.747M

Buyers (Bids)

No. Vol. Price($)
4 98685 9.3¢
 

Sellers (Offers)

Price($) Vol. No.
9.6¢ 149351 2
View Market Depth
Last trade - 15.06pm 16/06/2025 (20 minute delay) ?
GLN (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.