So, between the 01st to 26th of April, they produced 900 tonnes - then by the 30th of April will be roughly 1040 tonnes this month.
By July they expect to reach 60Ktpa, meaning 5000 tonnes per month.
So the throughput gap is: 5000 tonnes - 1040 tonnes = 3960 tonnes a month. In other words, by now the production throughput is 20.8% of the expected by July. I hope the new tank and PPIP will cover that 80% gap on time, and not run out of cash.